ADEM Proposes $18,000 Civil Penalty for Baldwin County Sewer Service Over Fort Morgan Plant Violations
R. Peevy • September 10, 2026
BCSS and Fort Morgan residents have history of disagreement

Fort Morgan, Ala. — (GSN) — The Alabama Department of Environmental Management (ADEM) has proposed a Consent Order and an $18,000 civil penalty against Baldwin County Sewer Service (BCSS), LLC, for multiple environmental violations at its Fort Morgan Treatment Plant.
According to the proposed Consent Order, the violations at the facility—located at 16763 AL Hwy 180 in Gulf Shores—include exceedances in flow volumes and Biological Oxygen Demand limits. ADEM also cited BCSS for unpermitted discharges in the form of Sanitary Sewer Overflows (SSOs) and a failure to report these SSOs to the Department within 24 hours of becoming aware of them.
If issued, the Consent Order will require BCSS to submit a detailed Engineering Report outlining corrective actions and a schedule-based Compliance Plan. The company must also submit a complete Underground Injection Control (UIC) permit modification application and a report exploring the feasibility of alternative wastewater discharge options. Members of the public have 30 days from the publication of the notice to submit comments or request a hearing.
A History of Conflict: The Fort Morgan Plant and Local Residents
The proposed penalty marks the latest chapter in the checkered history of the Fort Morgan plant, which has long been a focal point of intense legal and environmental disputes between BCSS, local residents, and the City of Gulf Shores.
The plant was originally constructed in 1986 in what was then an unzoned, unincorporated area of Baldwin County. Over the subsequent decades, residential neighborhoods grew directly around the facility. BCSS officials have argued that "the residential development has come to the facility," which was in operation long before the surrounding homes existed.
However, local residents and watchdog groups, notably the Little Lagoon Preservation Society (LLPS), have raised serious environmental and quality-of-life concerns. Tensions escalated dramatically in late 2021 when BCSS constructed a 1-million-gallon sludge processing pond on the property without obtaining a permit from the City of Gulf Shores.
The sludge pond was built less than 100 feet from a subdivision, subjecting neighboring residents in the Little Lagoon Mobile Home Park to severe odors and swarms of insects. In response, the City of Gulf Shores issued a cease-and-desist order in May 2022 to halt the use of the sludge pond, classification of which as an illegal expansion of a nonconforming use in a residential zone was upheld by the city's Zoning Board of Adjustment.
As ADEM's proposed Consent Order moves through its 30-day public comment period, the fate of the Fort Morgan plant continues to hang in the balance, caught between the utility's expansion goals and the determined resistance of local residents and municipal watchdogs.
ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT
PO BOX 301463 (Zip 36130-1463)
1400 Coliseum Boulevard (Zip 36110-2400)
Montgomery, Alabama 36130-1463
(334) 271-7700
PROPOSED CONSENT ORDER
Account Code: 212
Baldwin County
Pursuant to the provisions of the Alabama Environmental Management Act, the Alabama Department of Environmental Management is proposing to issue a Consent Order to Baldwin County Sewer Service, LLC for UIC Permit Number ALSI9902013, Fort Morgan Treatment Plant, located at 16763 AL Hwy 180, Gulf Shores, Baldwin County, Alabama.The violations noted in the Consent Order consist of exceedances in flow volumes and Biological Oxygen Demand limits. Other violations include unpermitted discharges in the form of Sanitary Sewer Overflows (“SSO”), and failure to submit required reports to the Department within 24 hours after becoming aware of a notifiable SSOs.
The Department is proposing a civil penalty in the amount of $18,000. The Order, if issued, would require Baldwin County Sewer Service, LLC to submit an Engineering Report that addresses corrective actions and outlines a Compliance Plan with a schedule for implementation of necessary corrective actions, and a complete UIC permit modification application to achieve compliance with applicable rules, regulations, and Permit conditions. In addition, the Order would require Baldwin County Sewer Service, LLC to submit a report summarizing the feasibility of an alternate wastewater discharge option.
Interested persons may submit written comments, including request for a hearing, within 30 days of the publication date of this notice to:
Alabama Department of Environmental Management
Attention: James H. Carlson
Chief of the Water Division
PO Box 301463
Montgomery, Alabama 36130-1463
The comment period shall end at the close of business 30 days from the publication date of this notice. A copy of the proposed order is available on the ADEM web page at http://adem.alabama.gov/public-notices or may be obtained by written request to the above address. A nominal fee for copying may be charged.
This notice is hereby given this 28th Day of August, 2026 by authorization of the Alabama Department of Environmental Management.