Gulf Shores Pedestrian Bridge Project Reaches Key Milestones

Gulf Shores News Staff • January 25, 2026

Project is almost halfway to completion

Construction on the City of Gulf Shores’ pedestrian bridge is progressing as planned, with crews reaching several visible milestones. City officials report steady progress on roadway work, bridge construction, and elevator towers. The project continues to move forward without significant delays. Officials say work remains on schedule according to the contract.


As of this update, the pedestrian bridge project is 47.4 percent complete under the contract schedule. Subcontractors are scheduled to return to active roadway construction on Monday, January 26. Their work will focus on revisions to the ALT 1 typical section and continued curb and gutter construction along ALT 2.


ALT 1 and ALT 2 refer to the two new approach roadway segments that will carry traffic to and from the pedestrian bridge and elevator towers on each side of the Intracoastal Waterway. They include the reconfigured travel lanes, curb and gutter, and sidewalk areas that tie the bridge landings back into the existing street network, and are being built in phases so local access can be maintained while construction continues.


Recent progress includes significant developments on both sides of the Intracoastal Waterway. On the north side, all 15 bridge pilings have been saw-cut. Crews have started removing material to reach the necessary elevation for pile cap installation.


On the south side of the bridge, contractors are preparing for the next phase of the structure. The first vertical section of the South Bridge Bent Columns is expected to be poured within the next two weeks. This step marks another key transition in the bridge’s framework.


Work on the elevator towers also reached an important milestone earlier this week. On Wednesday, January 21, crews completed the final vertical section pour for the South Elevator Tower. City officials described the pour as a major achievement for the project.


Pile driving work has also been completed on the North Elevator Tower. Contractors successfully installed two piles to repair Pile 11. With that work finished, all pile driving activities for the elevator towers are now complete.


Traffic restrictions remain in place as construction continues. East 2nd Street between 23rd Avenue and 24th Avenue is still limited to local traffic only. The restriction is expected to remain through mid-February while pavement, curb, gutter, and sidewalk work is finalized.


Traffic north of the Intracoastal Waterway is also limited to local access during ongoing ALT 2 construction. City officials noted that no utility relocation work was performed during the most recent reporting period.


Erosion control measures continue to be monitored and maintained throughout the site. Contractors are repairing best management practices as needed. A pump system remains in operation on the north side of the waterway to manage the pile pit area.


The pump system will stay in place until all piles are cut off and pile caps are completed. These measures are intended to protect surrounding areas while construction activities continue.


Looking ahead, pile driving crews are expected to finish cutting elevator piles on the north side soon. The contractor is anticipated to demobilize by early February. Work will also continue on the South Elevator Tower’s internal slabs and ALT 1 roadway revisions.


  • gulf shores news

    Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
Add As GOOGLE News Source
  • news in gulf shores

    Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • port at zekes

    Slide title

    Write your caption here
    Button
  • Slide title

    Write your caption here
    Button
  • saunders marine gulf shores

    Slide title

    Write your caption here
    Button
  • yabbas snack shack

    Slide title

    Write your caption here
    Button
  • freedom boat club orange beach

    Slide title

    Write your caption here
    Button
  • buzzcatz coffee

    Slide title

    Write your caption here
    Button

Recent Posts

Things To Do In Gulf Shores
By Jessica Taylor July 27, 2026
Whether you’re a local hunting for something fresh or a visitor eager to make the most of your beach holiday, you’ve come to the right place. This week’s lineup is full of adventures that make the Alabama Gulf Coast
BJ’s Wholesale Club
By R. Peevy July 27, 2026
Foley is set to welcome a major addition to its retail landscape in the fall of 2026 as BJ’s Wholesale Club prepares to open its doors. The new facility, located on a 14-acre site along the South Juniper Street Extension
Gulf Coast Chamber's Island Spirit Award
By Gulf Shores News Staff July 27, 2026
The Gulf Coast Chamber's Island Spirit Award committee, presented by Bluewater Exteriors, has announced Rocio Miranda-Garcia of De Soto's Seafood Kitchen as the recipient of the June 2026 Island Spirit Award. This prestigious honor is part of the chamber's ongoing tradition of recognizing non-management workers
Show More